Installing the Railings
Margin of Error: 1/4”
Most Common Mistakes
- Pickets not plumb.
- Top railing not level
- Pickets not evenly placed.
- Pickets too far apart.
You should get Adobe Flash Player so you can view our video.
There are many different styles of railings for decks. Choose a style according to your budget, time, and energy, as well as to the overall look and use of the deck. Different styles do different things. You can incorporate planters, benches, tables, and stairs into your design. A book on deck design or a ride around the neighborhood will give you some inspiration.
I have chosen to teach a rather simple design but one that is often used. If you are building something different from this, many of the procedures outlined here will still apply. If you are copying a design from an existing deck, a close inspection of the deck with sketchbook in hand should enable you to understand how the railing is put together. The main thing you want to be sure of in installing a railing is its stability. There is nothing worse than building the entire deck railing, only to discover later that it is weak and unstable, and then always worrying when a guest at your barbeque is going to make an unexpected visit onto your lawn.
There are usually codes that apply to deck railings. If the deck is more than a certain distance from the ground, often 30 inches, a railing may be required. If the deck is closer to the ground, the railing may be optional. Also, the code will allow only a certain gap between the ballusters, sometimes called spindles, 4” - 9”, so that a child cannot slip through. The height of the railing is regulated, too - 36” - 42”. Be sure you check all of this before beginning.
The railing we are showing is constructed of 2 x 2 ballusters with a 2 x 4 top railing. This is a simple yet attractive railing. Since we are not tying the railing into the foundation posts (which is often the case), stability is a concern. We provide this stability by bolting the bottom of the ballusters to the band joists, using two Hot Dipped Galvinized lag screws, and by tying the railing into the house at several places.
First, cut all the ballusters. For aesthetic reasons we have put an angle cut on the top and bottom of each balluster. After the ballusters are cut, cut the 2 x 4 top rail. Try to use pieces that are long enough to span the entire length of each section. If the span is too long and two pieces are needed, you will need to join these two over a 2 x 4 picket for adequate bearing. Determine where this break should occur for the most balanced appearance. Also, where two sections of the deck come together, miter cut the top rail to cover any exposed end grain. This looks much better.
After all your pieces are cut, it is best to bolt the ballusters to the top rail and then install the entire assembly onto the deck Mark the top rail so that the ballusters will be property spaced. Then bolt the ballusters to the rail using lag screws that are as long as possible without poking through the back side of the railing (about 2 1/2”). Be sure that your marks are correct and that the ballusters are attached to the proper side of the marks. A balluster that is off will show clearly, once installed.
Also, at the bottom of each balluster drill two holes that are one size smaller than the lag screws that will hold the ballusters to the joists and band. Drill these holes so that they are as far apart as possible and yet at least 1 1/2” from the edge of the band and joists. You are now ready to install the entire assembly onto the deck. This is done by using two more lag screws at the base where the picket meets the joists and band. Again, use a 2 1/2” lag screw and, as always, be sure they are Hot Dip Galvinized, aluminum, or stainless steel so they will not rust. It is best to align the balluster/railing assembly so that it is in its exact location and to nail a few ballusters temporarily in place to hold it there. Then use a level to locate where each balluster will meet the band and joists. By using the level at each balluster, you can be sure that they will all be level and parallel to each other.
Uneven ballusters are easily noticed. It is imperative that the assembly be in its exact location before you start leveling the ballusters. If you need to move the assembly even slightly after the pickets are attached at the bottom, the entire assembly will look askew and will need to be redone. Once you have ascertained that it is in its exact location, and have leveled your pickets, hold the picket in place while you mark the location of the holes on the band and joists. Then drill these holes on the band and joists, again using a drill bit one size smaller than the shank of the lag screw. Then bolt the lag screws in, using a socket or crescent wrench. Do this around the entire deck until the railings are all in place. Where two railings intersect at their mitered cut railing top, drill pilot holes through one top railing into the other and then nail together with 10d HDG finishing nails, two from one direction and one from the other. Your railings should now be complete.




. Questions of a Do It Yourself nature should be submitted to our "